A 14-Month Warehouse Against a Lease Deadline
Industrial· SIPCOT Industrial Park, Chennai, TN· 2024

A 14-Month Warehouse Against a Lease Deadline

Structural steel, roofing, and civil works delivered against a hard lease-start deadline for a logistics operator.

The Challenge

The client's incoming lease with a national retailer had a fixed start date — any slippage in construction meant penalty clauses on a signed lease.

Our Solution

A single turnkey package covering steel, roofing, and civil works, run on a compressed but tightly sequenced 14-month program.

The Result

Handed over on schedule with zero lost-time safety incidents, and racking installation began the day after handover.

The brief

A third-party logistics operator had signed a lease with a national retail chain, committing to a fixed handover date for a large-format distribution warehouse at SIPCOT, Chennai. The lease carried financial penalties for late delivery — construction timeline was no longer just a schedule, it was a contractual obligation.

The challenge

At 14 months, the program was tight for the scope involved: structural steel fabrication and erection, long-span PEB roofing, high-load RCC flooring, and full site civil works, including dock infrastructure for an 18-bay yard. Any single delayed trade — steel fabrication, roofing, or flooring cure times — risked cascading into the lease date.

Our approach

We ran structural steel fabrication off-site in parallel with foundation and civil works on-site, so erection could begin the moment footings were ready rather than waiting on a sequential start. Roofing followed directly behind steel erection, bay by bay, so weather protection was in place early and interior trades could start without waiting for full building closure.

Scope of work

  • Structural steel fabrication and erection
  • PEB roofing and wall cladding
  • RCC flooring rated for high-bay racking loads
  • 18-bay dock yard, fire exits, and site civil works

The result

The building was handed over on the contracted date, with zero lost-time safety incidents across the full program. The client's racking contractor began installation the following day — the fastest handover-to-occupancy turnaround we've delivered on a project this size.

A 14-Month Warehouse Against a Lease Deadline — photo 1
A 14-Month Warehouse Against a Lease Deadline — photo 2