The brief
A local government body needed six blocks of a school campus re-roofed after years of monsoon leaks had damaged classroom ceilings. The only possible construction window was the school's term break — and the reopening date was fixed. There was no flexibility to extend into term time with students on campus.
The challenge
Re-roofing six separate blocks — including safe removal of aging asbestos sheeting under regulatory disposal requirements — is normally sequenced block by block. Done that way, this project would have run well past the reopening date.
Our approach
Instead of a sequential block-by-block approach, we split the crew across all six blocks in parallel from day one, with a dedicated asbestos-removal team working ahead of the roofing crews. Ceiling repair and repainting followed immediately behind roofing on each block, rather than waiting for all six roofs to finish first.
Scope of work
- Safe removal and regulated disposal of damaged asbestos sheeting
- New corrugated metal roofing across all six blocks
- Ceiling repair and repainting in affected classrooms
- Gutter and downpipe renewal to prevent future water pooling
The result
All six blocks were re-roofed, repaired, and repainted in three weeks — inside the term break, with the school reopening on schedule and no classrooms out of use.